CSP practice question: Management of change: field deviations during implementation
Question of the Day for Saturday, 21 November 2026
CSP · Program Management
At a PSM-covered unit, an approved MOC adds a 3-inch bypass around a feed control valve, with a hazard review, updated P&IDs and a pre-startup safety review set for tomorrow. During installation the contractor could not get the specified flanges and fitted a lower pressure class, rated above normal operating pressure but below the set pressure of the relief valve protecting the line. What should the CSP require before start-up?
Explanation
Paragraph (l)(2) requires the technical basis, the impact on safety and health and authorization to be addressed prior to any change, and a field substitution that departs from the approved design is a change the approved MOC never reviewed. Flanges rated below the relief set pressure can fail before the relief valve opens, so normal operating pressure is the wrong test; the design rating must be restored, or a re-engineered design reviewed and approved, before start-up, and (i)(2) requires the pre-startup safety review to confirm that construction and equipment are in accordance with design specifications and that modified facilities meet paragraph (l). Updating the P&IDs under (l)(4) records the change but neither reviews nor authorizes it, and deferring the fix to a turnaround runs the line outside its design basis. Source: 29 CFR 1910.119(l)(1), (l)(2), (l)(4) and (i)(2).Practise more questions like this
Studying for the CSP? The CSP11 blueprint explained · How to get the CSP · CSP practice exam by domain · All guides
Unofficial study aid: not affiliated with, endorsed by, or connected to the Board of Certified Safety Professionals (BCSP). ASP and CSP are trademarks of BCSP. Questions are original study items written for HSE HUB.