CSP practice question: Project Management
Question of the Day for Thursday, 3 September 2026
CSP · Program Management
Answer in HSE HUB Pro
The project 'triple constraint' (iron triangle) describes competing demands a manager must balance. Which set is correct?
ARisk, reward, and resources, with compliance affected by how these three are balanced together
BPeople, process, and technology, with strategy affected by how these three are balanced together
CScope, time (schedule), and cost (budget), with quality affected by how these three balance
DSafety, morale, and reputation, with profitability affected by how these three are balanced together
See the answer and the full explanation